Call any time for a free quote on your commercial project whether it's landscape management, landscape construction, or snow removal.

314.892.9500



 


 

AUGUSTINE HEIGHTS CHANNEL IMPROVEMENTS

PROJECT TYPE: Bio-Stabilization
CLIENT: City of Eureka
APPROX VALUE:   $400,00
DURATION: September 2005 - April 2006

PROJECT SUMMARY: 
Provide channel improvements to an unnamed tributary along 2,250 lineal feet of creek bank which included slope protection, grade control, and storm water outlets at designated points along the channel.  Planting and seeding of a variety of Missouri-native species was required to further restore the area in addition to maintenance of the vicinity to ensure establishment of the planted areas.

PROJECT SOLUTION:
Three methods of reinforcement were used to create the reinforced channel on this project.  The first was 700 feet of Ajax Bank Protection.  Essentially these large concrete blocks look like Legos which interlock together to form protective rows along the channel
.

The second method was to protect the slope with Geo Web, a plastic material with a honeycomb structure that is filled with dirt and plants (see photo and illustration below).  The plants take root and eventually grow into their own, natural form of reinforcement.  This type is not good for use along toe areas because of scouring during times of extreme flow.

That led to the third method, gabion baskets which were added to prevent scouring.  Gabion baskets are large PVC covered, galvanized steel baskets filled with rock (see photo 5 below).

Along the channel 30 large trees had to be removed but by the end of the project Ideal replaced them with 61 canopy trees.  Additionally 5,300 small plugs and Missouri-native bare root plants filled the Geo Web cells.  Some of the plants included a variety of sedges, rushes, zigzag and giant goldenrod, ferns, river bulrush and so on.  Of the 400 live stakes used tree varieties included river birch, alder, green ash, sandbar and black willows, silky dogwoods, and buttonbush. 

All projects of this type require permits from the Department of Natural Resources before construction may proceed.

SPECIAL CONSIDERATIONS:
This project was made extremely difficult by six feet of mud in the creek bed which literally swallowed equipment and made access through the channel very complicated.  Countless hours of remediation were necessary in order to get equipment into place and a by-pass pump was set up to drain water from areas where work was underway.

The first two months went very smoothly but rains slowed what should have been the final two weeks of the project into two additional months.

PHOTOS:

Remediation underway to make the creek passable for heavy equipment.
A shot of the muddy conditions at the jobsite.
Initial work begins in order to stabilize the creek and get the project underway with A-Jacks and coir logs lining the channel.
The creek conditions before work began.
Gabion baskets are placed along the bottom of the creek to prevent scouring.
A glimpse of the progress several weeks into the project.
Filter fabric against the bank prevents infiltration of the soil.
Heavy equipment in the creek bed alongside the gabion baskets.
 
 



Photo of a Geoweb wall.  The purpose is to plant the pockets in the face to allow vegetation to grow.


HOME
          ABOUT US          MAINTENANCE          CONSTRUCTION          CONTACT US
©2008 Ideal Landscape Group, All Rights Reserved.       Privacy Policy  |  Legal Information  |