Call any time for a free quote on your commercial project whether it's landscape management, landscape construction, or snow removal.

314.892.9500



 


 

GRAY AND OAK DRIVE STORM CHANNEL

PROJECT TYPE: Bio-Stabilization
CLIENT: Metropolitan Sewer District
APPROX VALUE:   $150,000

BIO-STABILIZATION
Due to both ecological as well as engineering factors, concrete reinforced flumes are seldom used for storm channel reinforcement today.  A very new trend is called Bio-Stabilization.  Depending on the hydraulics involved, it was discovered that simple concrete channels actually increased the speed of water flow and made erosion worse farther down the line.  For this reason engineers devised bio-stabilization - or the process where by natural reinforcement methods (of which there are many) may be combined with synthetic elements to create both a more stabile and ecologically friendly storm channel.  Over time nature does the job of reinforcing the channel as the plants grow and root themselves into the channel wall.

PROJECT SUMMARY: 
At the intersection of Gray and Oak Drives significant erosion was occurring at the bend in an MSD storm channel due to severe runoff.  All creeks in this area are experiencing such failure due to continued residential development.

PROJECT SOLUTION:
For this project three types of reinforcement were used.  The first was pre-cast channel liners which are essentially blocks filled with dozens of holes which line the channel and then are filled with soil.  The second is a live crib wall, or essentially green logs stacked in an interlocking Lincoln-log fashion with soil placed behind and between to allow live stakes (young, green trees) to grown and take root among them.  The third method is a rock revetment, or simply heavy stone boulders and rock placed to help slow water flow.

To control erosion within the channel section, Ideal work crews installed 2,362 Pavelock pavers, 115 linear feet of crib wall, and over 5,000 live stake plantings.  Workers also installed 600 square yards of sod and several dozen container plants to beautify and restore the bank areas which abutted residential property.

As a testament to the strength of these natural reinforcements, a severe storm shortly after completion did no structural damage.  While some minor aesthetic plants and sod were washed away, the bio-stabilization easily did its job even very soon after construction.

SPECIAL CONSIDERATIONS:
Since the area was completely lined by residential neighborhoods, special permits and easements needed to be obtained.  Additionally this meant there was difficult access for crews and equipment.  Finally, residential property (yards, etc.) needed to be restored to original or better condition upon completion.

PHOTOS:

Near project completion, heavy rains soaked the site and filled the creek.  The heavy revetment can be seen lining the channel along with the armor block.  Restored sod is in the foreground.
 
A close up of the Armor Lock paver system.
Organized chaos as excavation begins and the project gets underway.
The Lincoln Log type structure is part of the live crib wall.
A nice shot of the stone revetment along the channel.
A close up of "live whips", of live pieces of tree which will eventually begin growing on their own.
Another view of the live whips and stone revetment.
A shot of the continuing rains two days after the project wrapped up.  In the foreground the holes can be seen where large container plants were placed but washed downstream.


HOME
          ABOUT US          MAINTENANCE          CONSTRUCTION          CONTACT US
©2008 Ideal Landscape Group, All Rights Reserved.       Privacy Policy  |  Legal Information  |