Call any time for a free quote on your commercial project whether it's landscape management, landscape construction, or snow removal.

314.892.9500



 


 

METROLINK, EROSION CONTROL

PROJECT TYPE: Panel Retaining Wall
CLIENT: Metrolink
APPROX VALUE:   $500,000
DURATION: October 2005 - February 2006
SIZE: 1500 lineal feet

PROJECT SUMMARY: 
More than 1500 feet of hillside between Compton Avenue and Ewing Avenue was eroding.  During times of heavy rain soil would run down the hillside and infiltrate the existing Metrolink tracks, slowing the trains.  This project had nothing to do with the Cross County Extension.

PROJECT SOLUTION:
Pre-cast panel walls were built along the hillside to stop erosion.  Panels were 3 feet by 15 feet in size.  A drainage pipe was added to catch water from the tracks and a swale was constructed to catch water from along the hillside.

SPECIAL CONSIDERATIONS:
A major concern during the duration of this project was safety.  Metrolink trains run on an 800 volt DC current, different than the AC current used in households.  During construction Ideal excavation equipment would have to come dangerously close to these lines.  All members of the construction team as well as project managers attended safety classes regarding this specific hazard.  An additional requirement was a flagman to slow the trains as they approached the construction site

PROJECT RECORD:

 
   
   
   
   
   


HOME